CS605 QUIZ NO 2 SOLVED 100% VERIFIED BY ADMIN (FINAL TERM SYLLABUS)
Q1: Configuration Status Reporting (CSR) reports on:
A) What happened?
B) Who did it?
C) When did it happen?
D) All of the given options (100% Sure)
Q2: The information items defined by Engineering Change Order (ECO) include:
A) Criteria for review and audit (100% Sure)
B) Work breakdown structure
C) The project Task Network
D) The change control test case
Q3: __________ is one of the techniques to prepare project schedule once we have defined "task network".
A) Program evaluation and review techniques (PERT) (100% Sure)
B) Critical Communication path method (CCPM)
C) System resource negotiation method (SRNM)
D) Strategic Schedule Development Technique (SSDT)
Q4: CPM stands for:
A) Critical Project Measure
B) Critical Path Method (100% Sure)
C) Common Project Measure
D) Critical Planning Model
Q5: BAC stands for:
A) Budgeted Analysis Cost
B) Budget And Cost
C) Budget at compilation
D) Budget at Completion (100% Sure)
Q6: The third digit (i.e. "Z") of the realease version number format is called:
A) Major Release Number
B) Feature Release Number
C) Defect Repair Number (100% Sure)
D) None of the given options
Q7: The equation to find out the Avaliability of software is:
A) Avaliability=(MTTF x MTTBF)/100
B) Avaliability=(MTTF / MTTBF)/100 (100% Sure)
C) Avaliability=(MTTF + MTTBF)/100
D) Avaliability=(MTTF - MTTBF)/100
Q8: Schedule Performance Index (SPI) is equal to:
A) BCWP/BCWS (100% Sure)
B) BCWP*BCWS
C) BCWP+BCWS
D) BCWP-BCWS
Q9: Following are effective guidelines for Review EXCEPT:
A) We need to review the product not the producer
B) Be sensitive to personal egos
C) Errors should be pointed out gently
D) Tone should be high and strict (100% Sure)
Q10: The basic idea behind Software configuration management is:
A) To manage and control the change (100% Sure)
B) To efficiently allocate the resources
C) To properly manage status reporting
D) None of the given options